Case Study: CareFirst Corporate Office Decommission
Time & Location:
- Owings Mills, MD
- Project size: 520 cubicles, 18 offices, 4 conference rooms
- 2024

Project Overview:
CareFirst required the full decommissioning of one of their corporate offices, including the removal of office furniture, IT equipment, and infrastructure. The project involved large-scale disassembly and disposal under a tight 12-day timeline, with strict requirements for recycling and safe handling.
Execution & Strategy:
HMS provided a trained supervisory team and movers equipped to manage large-scale decommissioning. The scope included:
- Furniture & Equipment Removal: Cleared all contents for recycling/disposal.
- Cubicle & Office Disassembly: Dismantled 530 cubicles, 18 offices, and 4 conference tables.
- Technology Disconnects: Safely disconnected and collected computers, docking stations, phones, headsets, and monitors.
- Electrical Systems: Managed the disconnection of power poles and whips.
Outcome:
- Full decommission of the CareFirst corporate office location completed in 12 working days.
- Safe removal and recycling of all office assets.
- CareFirst praised HMS for efficiency, professionalism, and adherence to sustainability goals.